Is it possible to edit/correct sample amounts etc. once a sequence has been run?

Hi All,

I performed a run but forgot to add sample amounts to the sequence. Is it possible to edit/correct sample amounts etc. once a sequence has been run?

Kind regards,

Ethel

  • Hi

    You don't say which software you're using, but the answer is yes anyway.

    • In Chemstation - you can edit the Sequence Table in the Data Analysis view
    • In OpenLab CDS - you can edit the Injection List in the Data Analysis application
    • In EZChrom - you can edit the Result Sequence.

    In all three cases, you can reprocess the results with the correct sample amounts.

    Hope that one of those makes sense.

    /Andy